Value: £880K
An empty corner plot of land previously occupied by a public house with planning approval benefits to build 10 – 2-bedroom apartments with 5nr. car parking spaces but due to expire in less than 6 months period.
The Brief
- Development required to start prior to the expiry of the planning approval
- Assistance with appointing a Principle Contractor
- Provision of Contract Administration and Project Manager role
- Management of Core Design team
The Solution
- Due to time constraint, able to source and negotiated the contract sum prior to appointing the Principle Contractor
- Revised the construction method and sequence to accommodate delays, predominately due to revised structural design and improper fill of previous public house basement
Achievements
Development started prior to expiry of planning approval, with a subsequent ‘Non-Material Amendments’ submitted to revise design due to value engineering